Tech Journal · #357

micro-coaxial

Laser Stripping Micro-Coax: Process and Inspection

EDPcable Engineering Team2026-06-02
Laser Stripping Micro-Coax: Process and Inspection
ARTICLE · #3572026-06-02

Summary

Laser stripping prepares micro-coax terminations by removing selected jacket, shield or dielectric material. It can reduce the mechanical force applied by a cutting blade, but a non-contact process still needs qualification for the actual material stack. This guide explains why jacket removal, shield cutting and dielectric stripping are separate operations, how to compare laser and mechanical methods, and which evidence to collect before releasing a process. A hypothetical strip-length example shows why matching two exposed lengths does not confirm the remaining dielectric land. Use the inspection checklist and RFQ inputs to define a trial; neither wire gauge nor connector pitch alone proves that a laser process is necessary or that an assembly will pass its electrical requirements.

1. What Laser Stripping Does

Laser stripping uses focused light to cut or remove a selected cable layer before termination. Micro-coax commonly has an outer jacket, metallic shield, dielectric and center conductor. Preparing these layers requires separate locations and acceptance criteria. Removing insulation and cutting a metal shield are different operations; one recipe should not be assumed to handle both.

A non-contact beam removes blade contact from that operation. It does not establish that the remaining conductor, plating or dielectric is undamaged. Laser Wire Solutions' process FAQ explains that the technology, wavelength and parameters must match the insulation and conductor combination.

2. Choose the Process from the Construction

There is no universal 40 AWG or 0.25 mm connector-pitch threshold that makes laser stripping mandatory. Conductor gauge, cable outside diameter and connector pitch describe different features. Obtain the cable drawing and actual samples before comparing methods.

Decision inputLaser trialMechanical trial
Layer material and adhesionCheck absorption, removal and residue on actual materialCheck cutting and pull-off behavior on actual material
Shield and dielectric geometryQualify each removal boundary and underlying layerQualify blade depth, centering and pull-off effects
Cable or ribbon positioningVerify fixture location and presentation repeatabilityVerify guides, clamping and tool alignment
Production requirementCompare accepted output, inspection and handling timeCompare accepted output, tool maintenance and handling time

Compare inspected samples made to the same drawing. A cleaner-looking surface alone does not establish electrical performance or production yield. This is an engineering selection method, not a claim that either process is qualified for a particular EDPcable assembly.

3. Separate Jacket, Shield and Dielectric Operations

The manufacturer's micro-coax process overview describes a system using CO₂ for polymer layers and UV for shield cutting. That is one equipment architecture, not a universal recipe for every polymer, plating or shield construction.

First define the required exposed regions from the termination drawing. Then trial the actual material stack with controlled position, focus, energy delivery and pass sequence. Include fixture condition and the extraction arrangement in the setup record. Inspect after each layer so a later operation does not hide the origin of a defect. Store the approved recipe together with cable and drawing revisions; a material or geometry change requires an assessment before reusing it.

4. Worked Example: Check the Dielectric Land

Consider an illustrative stepped end measured from one common cut-end datum: the jacket boundary is 3.0 mm from the end, the shield boundary is 2.0 mm, and the dielectric boundary is 0.8 mm. The exposed center conductor is 0.8 mm long. The dielectric land between the conductor exposure and shield edge is 2.0 − 0.8 = 1.2 mm; the exposed shield region is 3.0 − 2.0 = 1.0 mm.

These are hypothetical dimensions, not recommended strip lengths or tolerances. If an operator instead places the dielectric boundary at 1.4 mm while retaining the 2.0 mm shield boundary, the land falls to 0.6 mm. A report listing only jacket and shield lengths would miss that change. Measure all boundaries from the drawing's datum, record their tolerances, and obtain the termination owner's approval. This arithmetic does not predict impedance or qualify the transition.

5. Six Checks Before Process Release

The following is a proposed review checklist. Sampling, magnification, test methods and limits belong in the approved inspection plan.

CheckEvidence to retainHold the lot when
Strip boundaries and dielectric landMeasurements against the same drawing datumA required boundary or tolerance is missing or outside its limit
Center conductor and platingMagnified views around the exposed region; agreed damage criteriaA nick, deformation or suspicious surface change is unresolved
Remaining shieldViews of the cut edge and retained shield; check loose strandsAn incomplete cut, displaced strand or possible short is unresolved
Dielectric and residueViews of the land, boundary and exposed surfacesResidue, recession or apparent thermal damage lacks an accepted disposition
Setup repeatabilitySamples linked to cable lot, fixture, recipe and drawing revisionResults drift or the setup differs from the qualified configuration
Finished terminationContinuity/isolation and application-specific electrical or mechanical resultsRequired tests, limits or responsibility have not been agreed

Continuity does not measure the high-frequency transition. Add signal-integrity or durability verification where the design requires it. A supplier equipment specification does not validate the finished harness, medical device or sterilization process.

6. What to Send for a Process Trial

Provide cable manufacturer and part number, construction and material information, samples, termination drawing revision, required exposed regions and tolerances, connector or PCB details, volumes, and the inspection/test plan. Identify who approves deviations and which changes trigger a new trial. The manufacturer FAQ also calls for suitable extraction to control processing fumes and particles; the equipment supplier must assess the actual workstation.

For project scope and deliverables, use Laser-Stripped Micro-Coax. For construction terminology, read What Is a Micro-Coaxial Cable; use the cable drawing guide to define datums and revisions. Keep process education here and assembly-specific requirements in the project documents.

8. Engineering References

FAQ04

Frequently asked questions

  • Does laser stripping damage the center conductor?

    A suitable process can remove insulation without blade contact, but damage-free results must be established on the actual cable. Match the wavelength and recipe to the materials, then inspect the conductor, plating and dielectric against agreed criteria.

  • Does 40 AWG or 0.25 mm pitch require laser stripping?

    Those dimensions alone do not select the process. Gauge describes the conductor and pitch describes contact spacing. Evaluate the cable construction, exposed geometry, handling and inspected trial results before choosing a method.

  • Can the same laser recipe remove the jacket and metal shield?

    Do not assume it can. Polymer removal and metallic shield cutting interact with different materials. Qualify each operation and its effect on the underlying layer for the actual equipment and cable.

  • What should be inspected after stripping?

    Record all strip boundaries and the remaining dielectric land, conductor/plating condition, shield strands and residue. Link samples to the setup revision and verify the finished termination using the agreed electrical and mechanical plan. Continuity alone does not qualify signal integrity.

Last updated: 2026-10-17
SEC · 03Related applications

Related applications